1996 - Establishment
PT. Komatsu Remanufacturing Asia was established on December 17.1996, with capitalization between 2 stockholders, UT (51%) and KAP (49%)
1997 - Sudirman Plant establishment
  • Trial Operation on May 1997 at Workshop PT UT Samarinda Branch (Engine Production Only)
  • PT UT invest for KRA Building and Facility in Balikpapan
  • Moving to Balikpapan on December 03. 1997
  • KRA Man Power 16
1998 - Balikpapan operation
  • Start Operation in Balikpapan
  • Engine & Non Engine Production
  • KRA Man Power : 20
2000 - Warehouse & machining establishment
  • Build Warehouse & Machining Shop
  • KRA Man Power : 39
2002 - Main Office establishment
  • Build Main Office
  • KRA Man Power : 39
2004 - FMC Transaction
  • FMC Contract
  • KRA Man Power : 63
2007 - Mulawarman Plant establishment
  • Established 2nd Plant for Power Train/Electric Motor
  • SAP 4.7 Implementation
  • KRA Man Power : 94
2008 - Mechanic Management Program
  • Preparation Development Mechanic by Mechanic Management Program (MMP)
  • Build Warehouse at 2nd Plant
  • KRA Man Power : 151
2009 - Mulawarman Plant workshop expansion
  • Workshop expansion at 2nd Plant
  • Additional New FMC Contract with PT UT
  • Move Electric Motor production to UT
  • KRA Man Power : 174
2010 - Balikpapan Plant establishment
  • Transfer 2% share from UT to KAP/KI
  • Construct Balikpapan Plant for Engine
  • Move Electric Motor production to UT
  • KRA Man Power : 213
2011 - Factory Operation and CKD implementation
  • Start operation Balikpapan Plant ( Engine & machining shop)
  • Factory operation model implementation
  • CKD Parts order implementation
  • Change of Financial Year Jan-Dec to Apr-Mar
  • SAP upgrade to ECC 6.0
  • KRA Man Power : 263
2012 - CHAMPIONS introduction
  • Cost Reduction Project
  • Enhancement Salvaging Technology
  • CHAMPIONS Culture
  • KRA Man Power : 261
2013 - KMSI Transaction
  • KMSI Transaction
  • OX Project
  • Innovation Convention
  • KRA Man Power : 314